Open for responses
Y1DZ--Project Number 657-507, Correct Seismic Deficiencies for Building 14, Marion VAMC, Illinois Construction of New Boiler Plant and Demolition of Existing
VETERANS AFFAIRS, DEPARTMENT OF
Notice type
Solicitation
Solicitation #
36C10F26R0085
NAICS
236220
PSC
Y1DZ
Set-aside
Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
Posted
November 17, 2026
Response due
December 11, 2026
Place of performance
Marion, IL
Description
Above Group, Inc.
305 East Dr. Suite H
Melbourne, FL 32904
(321) 345-9026
www.abovegroupinc.com
Department of Veterans Affairs
2401 West Main St.
Marion, IL 62959
Correct Seismic Deficiencies
Building 14
VAMC Marion, IL
Final Bid Specifications
Contract No. 36C10F25C50004 | Project No. 657-507
6/16/2026
-- 1 of 1948 --
657-507
Correct Seismic Deficiencies Building 14
Marion VAMC
DESIGNER OF RECORD STAMP PAGE
DESIGNER OF RECORD STAMP PAGE
ARCHITECT OF RECORD: CIVIL ENGINEER OF RECORD:
STRUCTURAL ENGINEER OF RECORD: MECHANICAL ENGINEER OF RECORD:
ELECTRICAL ENGINEER OF RECORD: FIRE PROTECTION ENGINEER OF RECORD:
04/22/26
PROGRESS PRINT
NOT FOR CONSTRUCTION
RDC/JPA ARCHITECTURE
4/22/2026 4:57:10 PM
JASON
H.
ROSS
2118221
I
O
H
O F
O
E
T
A
T
S
R
E
G
I
S
E
T
R E D
R
A
C
H
T
I
E
C
T
TECHNOLOGY DESIGNER OF RECORD:
-- 2 of 1948 --
06-01-24
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements for Major Projects 05-24
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 12-23
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 01-21
02 82 13.41 Asbestos Abatement for Total Demolition Project 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 12 50 Buckling Restrained Braces
05 31 00 Steel Decking 01-21
05 36 00 Composite Metal Decking 01-21
05 40 00 Cold-Formed Metal Framing 01-21
05 51 00 Metal Stairs 01-21
-- 3 of 1948 --
06-01-24
00 01 10-2
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 41 16 Plastic Laminate Clad Architectural Cabinets
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 Bituminous Dampproofing 01-21
07 12 00 Built-Up Bituminous Waterproofing 01-21
07 13 00 Sheet Waterproofing 01-21
07 13 52 Modified Bituminous Sheet Waterproofing 01-21
07 21 13 Thermal Insulation 01-21
07 22 00 Roof and Deck Insulation 01-21
07 24 00 Exterior Insulation and Finish Systems 01-21
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 01-21
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 71 00 Roof Specialties 01-21
07 72 00 Roof Accessories 01-21
07 81 00 Applied Fireproofing 07-23
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 31 13 Access Doors and Frames 04-22
08 33 00 Coiling Doors and Grilles 01-21
08 36 13 Sectional Doors 01-21
08 41 13 Aluminum-Framed Entrances and Storefronts 01-21
08 44 13 Glazed Aluminum Curtain Walls 04-20
08 56 53 Blast Resistant Windows 01-21
08 71 00 Door Hardware 03-24
08 80 00 Glazing 01-21
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 67 23.20 Resinous (Epoxy Base) With Vinyl Chip Broadcast (RES-2) 12-21
09 67 23.60 Resinous Urethane and Epoxy Mortar Flooring (RES-6A and RES 6B) 01-21
09 91 00 Painting 01-21
-- 4 of 1948 --
06-01-24
00 01 10-3
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21
10 21 16 Shower and Dressing Compartments 01-21
10 26 00 Wall and Door Protection 01-21
10 28 00 Toilet, Bath, and Laundry Accessories 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
10 51 13 Metal Lockers 01-21
DIVISION 11- Equipment
11 05 01 Owner Furnished /Contractor Installed Equipment
DIVISION 12 – FURNISHINGS
12 31 00 Manufactured Metal Casework 01-21
12 36 00 Countertops 12-23
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-21
DIVISION 14– CONVEYING EQUIPEMENT
14 45 00 Vehicle Lifts
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
22 05 12 General Motor Requirements for Plumbing Equipment 09-20
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 05-21
22 11 23 Domestic Water Pumps 09-15
22 13 00 Facility Sanitary and Vent Piping 09-20
22 13 23 Sanitary Waste Interceptors 09-20
22 13 29.13 Wet-Pit Mounted, Vertical Sewerage Pumps 09-20
22 14 00 Facility Storm Drainage 09-15
22 14 29 Sump Pumps 09-15
22 15 00 General Service Compressed-Air Systems 09-20
22 31 11 Water Softeners 09-15
22 34 00 Fuel-Fired Domestic Water Heaters 09-20
22 40 00 Plumbing Fixtures 05-24
-- 5 of 1948 --
06-01-24
00 01 10-4
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 10 Common Work Results for Boiler Plant and Steam Generation 06-24
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 03-23
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 03-23
23 05 51 Noise and Vibra…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Open opportunities in NAICS 236220
DOJ Phase II Renovation
JUSTICE, DEPARTMENT OF · Special Notice · due December 11, 2026
Winder Roof Drain Emergency Repairs
GENERAL SERVICES ADMINISTRATION · Justification
Apache Alert Mission Complex
DEPT OF DEFENSE · Solicitation · due January 8, 2027
Notice - Brand Name Justification for Lackland and Randolph
DEPT OF DEFENSE · Special Notice · due December 17, 2026
Child Development Center (CDC), Tinker Air Force Base, Oklahoma
DEPT OF DEFENSE · Solicitation · due December 1, 2026
Y1AA--890CM3013 Design Build (DB) Services for Renovation of Renovation of Historic Lodge/Administration Building at Fort McPherson National Cemetery
VETERANS AFFAIRS, DEPARTMENT OF · Sources Sought · due November 24, 2026