Z1DZ--695-22-123 Upgrade N Campus Medium Voltage Feeders
VETERANS AFFAIRS, DEPARTMENT OF
Notice type
Solicitation
Solicitation #
36C25226B0023
NAICS
238210
PSC
Z1DZ
Posted
July 23, 2026
Response due
July 22, 2026
What this opportunity is
The Department of Veterans Affairs is buying construction services to upgrade medium voltage feeders at the Clement J. Zablocki VA Medical Center. This solicitation suits businesses classified under NAICS code 238210. As a solicitation notice, this means that interested businesses should prepare to bid on the project rather than simply tracking its progress.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
PROJECT NO: 695-22-123
PROJECT NAME: Upgrade North Campus Medium Voltage Feeders
Clement J. Zablocki VA Medical Center
Upgrade North Campus Medium Voltage Feeders
Project 695-22-123
Statement of Work
October 7, 2025
US Department of Veterans Affairs
Clement J. Zablocki VA Medical Center
5000 W. National Ave.
Milwaukee, WI 53295-0001
STATEMENT OF WORK
Prepared by:
Facility Management Division
-- 1 of 4 --
Page 2 of 4
I. General Description
Provide Construction Services for Project 695-22-123 Upgrade North Campus Medium
Voltage Feeders
II. General Project Scope
1. Contractor shall furnish all labor, materials, equipment, qualified supervision, and all
items designated in this contract in accordance with the specifications and drawings to
complete Project 695-22-123 Upgrade North Campus Medium Voltage Feeders.
2. The general scope of the project involves:
i. Converting the Clement J. Zablocki VA North Campus Electrical Distribution System
from a Radial System to a Composite Primary Loop Radial System.
ii. Addition and replacement of select pad-mounted electrical distribution equipment
and associated components.
iii. Addition and replacement of select underground medium voltage feeders and
associated electrical fittings.
iv. Trenching and installation of new duct banks.
v. Integration of kirk-key interlock system.
vi. Addition and replacement of current transducer fault indicators.
vii. Detailed project phasing, sequencing, and outage planning to mitigate impacts to
buildings, medical center operations, and vehicle traffic/accessibility.
viii. Thorough utility survey services to develop and deliver a comprehensive utility
survey report, recording precise geographic location and depth information (where
attainable) of the North Campus Electrical Distribution System. This utility survey
report shall be delivered along with the as-builts.
3. The VA anticipates a minimum of 60 calendar days for processing long lead time
equipment and material submittals. See Section III Phase 0 below.
4. All work following the Notice to Proceed shall be completed within 410 calendar days.
-- 2 of 4 --
Page 3 of 4
III. Project Duration/Phases
1. Phase 0: Preliminary Work Phase
i. Provide submittals for long lead time equipment and materials. Promptly order long
lead time equipment and materials once the submittals have been approved by the
VA. Once long lead time equipment and materials have been ordered, the project
shall be placed onto suspension in order to preserve contract days. The suspension
duration shall be subject to the lead times and critical path planning.
The VA anticipates a minimum of 60 calendar days for the completion of Phase 0,
including the submission of the long lead time submittals, and the review and
approval of the submittals.
Once suspension is lifted, the project shall be constructed within a single year. The
construction of the project shall not overlap into multiple years, specifically the
construction phase. Provide contingencies for maintaining communication with the
VA during the suspension.
2. Notice To Proceed/Pre-construction Meeting
i. Once long lead time equipment and materials are anticipated to arrive and a
construction mobilization date can be established, the contract suspension shall be
lifted, and the VA will issue a Notice To Proceed (NTP) and schedule a Pre-
construction Meeting with the Contractor.
3. Phase 1: Pre-Construction Period (A)
i. Duration is 30 calendar days and shall not exceed NTP + 30 calendar days. Within
this period the contract shall submit the following and schedule a review meeting
with the COR and VA Safety (as applicable per the specification requirements):
a. Construction Schedule (Initial) – 01 32 16.15
b. Accident Prevention Plan – 01 35 26
4. Phase 2: Pre-Construction Period (B)
i. Duration is 30 calendar days and shall not exceed NTP + 60 calendar days. Within
this period the contractor shall submit the following Pre-Construction Submittals (as
applicable per the specification requirements):
a. Construction Site Security Plan – 01 00 00
b. Construction Phasing Plan(s) – 01 00 00
c. Existing Conditions Survey – 01 00 00
d. Obtain PIV Badges – 01 01 10-SN
e. Contractor’s Impact Statement – 01 01 10-SN
f. Contractor Checklist – 01 01 10-SN
g. Submittal Register – 01 33 23
h. Quality Control Plan – 01 33 23
i. Schedule of Values – 01 33 23
j. Activity Hazard Analyses – 01 35 26
-- 3 of 4 --
Page 4 of 4
k. SSHO and CP List for the Project – 01 35 26
l. OSHA Certificates, Licenses, and Training Documents – 01 35 26
m. Fire Safety Plan – 01 35 26
n. Construction Waste Management Plan – 01 74 19
5. Phase 3: Pre-Construction VA Review Period/Construction Kickoff Meeting
i. Duration is 30 calendar days and shall not exceed NTP + 90 calendar days. Within
this period the VA shall complete review of all Contractor Pre-Construction
Submittals.
Once all Pre-Construction Submittals have been approved and the Contractor is
ready to mobilize, the VA will schedule a Construction Kickoff Meeting with the
Contractor.
6. Phase 4: Construction Period
i. Duration is anticipated to be 245 calendar days and shall be completed no later than
NTP + 335 calendar days. All applicable documentation in Phases 1, 2, 3, and any
other submittals required to mobilize must be approved by the COR prior to
commencement of work by the Contractor. No demolition or construction shall be
started without COR review and approval of those items listed in the Pre-
Construction Period unless authorized in writing by the COR or the CO.
7. Phase 5: Post-Substantial Completion Period
i. Duration is anticipated to be 75 calendar days and shall be completed no later than
NTP + 410 calendar days.
The Contractor shall provide all required materials within 45 days of reaching Post
Substantial Completion (NTP + 380 calendar days). The Contractor shall provide the
following:
a. Inspection and Approval by the COR and/or the CO
b. Final Approval and Benefic…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238210)
HELENA NATIONAL FOREST - Solar System Install on Existing Well
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 6, 2026
Z1DA--Project No. 552-26-202 - Replace Overhead Paging System
VETERANS AFFAIRS, DEPARTMENT OF · Solicitation · due August 5, 2026
US Coast Guard Air Station Savannah Generator
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 19, 2026
1788 - Hanscom AFB HNJ Lundy AV Upgrade
DEPT OF DEFENSE · Solicitation · due August 21, 2026
FY26 Installation of New 3-Phase Primary Underground Electrical Service Ellington Field, TX
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 29, 2026