What this opportunity is
The US Coast Guard is soliciting a total small business set-aside contract for general contracting requirements at Air Station Savannah in Georgia. The scope of work includes removal and disposal of the current emergency generator, installation of a new diesel generator, and replacement of the automatic transfer switch. A site visit is required to inspect the work in place and verify the amount of work necessary to complete the job. Bidders should track the Combined Synopsis/Solicitation notice, as it does not require a separate solicitation notice.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Scope of Work for General Contracting Requirements
At Air Station Savannah, GA
1.1 SCOPE
The scope of work for this project includes: removal and disposal of the current emergency
generator in the hangar (Bldg #830) and the automatic transfer switch. Contractor shall remove
old unit, install new diesel generator and secure in place. All exhaust and ventilation ducting shall
be reconnected after install of new generator. The automatic transfer switch shall be replaced, and
reconnected. Acceptance is contingent on successful startup and full system testing to include a
successful full load bank test.
1.2 LOCATION OF SITE
USCG Air Station Savannah is located at: Hunter Army Airfield, 1297 North Lightning Road,
Savannah, GA. Phone: 912-652-4646.
1.3 EXAMINATION OF SITE
Site visit is required by prospective bidders to inspect the work in place and verify the amount of
work necessary to complete the job. Prospective bidders must schedule a site visit by emailing the
Air Station Facilities Engineer LCDR Dan Blaich at Daniel.J.Blaich@uscg.mil or the Public
Works Division Billy Hopkins, billy.r.hopkins@uscg.mil, or Paul Haddock
Paul.K.Haddock@uscg.mil, between the hours 0800-1530 on normal business days.
1.4 GENERAL REQUIREMENTS
The Contractor shall provide all labor and equipment to accomplish the scope of this work. The
Contractor shall coordinate with the Facilities Engineer LCDR Dan Blaich or Public Works Billy
Hopkins or Paul Haddock to ensure that disruptions to the normal operations of Air Station
Savannah are minimized.
1.5 PRODUCTS
Products to be furnished by the contractor:
Replacement narrow skid diesel generator for Kohler 60kw or industry standard no smaller
than 60KW.
1 150-Amp 480V automatic transfer switch.
1.6 INSTALLATION
Contractor shall remove and dispose of current generator and replace with new unit. All fuel lines,
vent fan ducting, and exhaust system connectors shall be reconnected to the new unit or replaced
by the contractor. Automatic transfer switch shall be removed and replaced. Contractor shall
perform a test startup and full load bank test prior to acceptance.
1.7 WORK COORDINATION
All work shall be coordinated with the Facilities Engineer LCDR Blaich or the Public Works
Department so there is minimal disruption to USCG Air Station Savannah during work.
-- 1 of 2 --
1.8 WORK HOURS
Unless otherwise negotiated, all other work called for by this specification shall be coordinated
during the hours of 7:00 am to 5:00 pm, Monday through Friday.
1.9 CONTRACTOR USE OF PREMISES
The Contractor will be working on a Coast Guard operational military installation. Become
familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from
the immediate area of work without the escort of the Air Station Facilities Engineer or other Public
Works department personnel, except for the use of the restrooms.
1.10 CLEANUP
The Contractor shall keep the work area, including storage area, free from accumulation of waste
materials and comply with all federal, state, and local regulations pertaining to storage, transport,
and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including
garbage cans, trash piles, or dumpsters. Any equipment or material removed, unless otherwise
directed by the Air Station Public Works department, shall become the property of the Contractor
and shall be transported from the site.
1.11 SECURITY
The Contractor shall comply with all regulations set forth by Hunter Army Airfield. A full list of
requirements to access base can be found at
https://home.army.mil/stewart/about/Garrison/DES/visitor-information
1.12 IDENTIFICATION
All personnel shall carry proper identification (ID) when on site. Proper ID is as defined by Hunter
Army Airfield at https://home.army.mil/stewart/about/Garrison/DES/visitor-information
1.13 FINAL INSPECTION AND ACCEPTANCE
When the work is complete and ready for final inspection, contact the Air Station Facilities
Engineering Officer, LCDR Dan Blaich, at Daniel.J.Blaich@uscg.mil or the Public Works
Divison, Billy Hopkins or Paul Haddock, at billy.r.hopkins@uscg.mil or
Paul.K.Haddock@uscg.mil. Product shall only be accepted following system startup and full load
bank testing.
1.14 DELIVERY, STORAGE, AND HANDLING
Deliver materials to, store at site, and handle in a manner that will maintain the materials in their
original manufactured or fabricated condition until ready for use.
1.15 OPERATION AND MAINTENANCE MANUALS
Furnish an operation and maintenance manual for each item of equipment. The manual should be
complete in all respects for equipment, controls, accessories, and associated appurtenances
provided. A copy of the equipment warranties must also be provided.
-- 2 of 2 --
Source: SAM.gov, as posted. Verify the current solicitation before responding.