Awarded to TRADEMASTERS SERVICE, INC. on September 14, 2026
This is an award notice, not an open solicitation. Related open opportunities are listed below.
What this opportunity is
The Department of Defense is seeking a small business to provide a complete turnkey replacement of the split system HVAC unit serving the Tomb Guards Area at Arlington National Cemetery in Virginia. This project involves decommissioning the existing unit, installing a new high-efficiency system, and modifying ductwork with minimal impact on the historic structure. As this is a total small business set-aside and an award notice, interested contractors should focus on compliance with quality assurance standards and be prepared for a non-personal services contract, which requires no government supervision.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
PERFORMANCE WORK STATEMENT
(PWS)
Tomb – Guards Area – Replace HVAC Unit
(Split System)
Arlington National Cemetery (ANC)
Date: August 2026
PART 1: GENERAL INFORMATION
1. General
This is a non-personal services contract to provide a complete turnkey replacement
of the split system HVAC unit serving the Tomb Guards Area at Arlington National
Cemetery (ANC). The government shall not exercise any supervision or control over
the contract service providers performing the services herein. Such contract service
providers shall be accountable solely to the contractor who, in turn, is responsible to
the government.
1.1 Description of Services/Introduction
The contractor shall provide all personnel, equipment, supplies, facilities,
transportation, tools, materials, supervision, and other items and non-personal
services necessary to perform the complete decommissioning, demolition,
installation, commissioning, and testing of a new split system HVAC unit (condenser
and evaporator) to match existing capacity at the Tomb – Guards Area. The
contractor shall perform to the standards and specifications defined in this
Performance Work Statement (PWS).
1.2 Background
Arlington National Cemetery (ANC), a national shrine hosting 4–6 million visitors
annually, conducts approximately 6,000 funerals and 2,000 ceremonies yearly,
including high-profile events with dignitaries, heads of state, and media. The Tomb
of the Unknown Soldier is the symbolic heart of ANC, guarded 24/7 by the Tomb
-- 1 of 26 --
Guards (3rd U.S. Infantry Regiment, "The Old Guard"). Maintaining stable
environmental and climate controls within the Tomb Guards Area is critical to
support their continuous, high-profile operations. There is zero tolerance for
operational disruptions, noise violations, or system downtime during funerals or
ceremonies. The Contractor's services must reflect ANC's symbolic importance,
adhering to FAR 46.4, AR 702-11, and DoD 5000.02 for quality assurance.
1.3 Objectives
The objectives of this project are:
• Safely recover refrigerant and decommission the existing failing split system
HVAC unit.
• Procure and install a high-efficiency replacement split system HVAC unit in the
same physical footprint.
• Modify existing ductwork and electrical connections with minimal physical
impact to the historic structure.
• Install new stand-alone controls for independent local operation.
• Ensure zero operational interference with the Tomb Guards' ceremonial and
administrative duties.
1.4 Scope
The services to be performed involve the turnkey demolition of the old split system
and installation of a new, matched-capacity HVAC split system in the same physical
locations.
• Included Services: Refrigerant recovery; disconnecting of ductwork, piping, and
electrical; temporary removal of obstruction ductwork (as needed to access the
mechanical room); physical demolition and off-site disposal of the old condenser
and evaporator; installation of the new split system; running of new refrigerant
lines; pressure testing and dehydration; charging with low Global Warming
Potential (GWP) refrigerant; reconnection and modification of existing
ductwork/electrical; and installation of stand-alone controls.
• Specific Exclusions: This contract explicitly excludes Direct Digital Control
(DDC) integration work into the main Campus Building Automation System
(BAS), electrical service heavy-ups/capacity upgrades, independent design or
structural drawing generation, and any overtime or off-hours work unless pre-
authorized by the Contracting Officer (KO).
-- 2 of 26 --
1.5 Period of Performance
The period of performance shall be a total of thirty (30) calendar days from the date
of the Notice to Proceed (NTP), which includes a ten (10) day Phase-In period for
administrative onboarding, security vetting, and material coordination.
• Phase-In Period: 10 Days from NTP / Award Date.
• Project Execution: 20 Days from the end of the Phase-In Period.
1.6 General Information
1.6.1 Quality Control
Quality control is the responsibility of the contractor. The contractor is responsible
for the delivery of quality services and supplies to the government (see FAR 52.246-
1, Contractor Inspection Requirements).
The contractor shall develop, implement, and maintain an effective Quality Control
Plan (QCP) specific to this replacement project. The QCP shall implement
standardized procedures for monitoring, verifying, and documenting contract
performance to ensure all task requirements are met. The contractor’s QCP must
contain a systematic approach to monitor operations to ensure acceptable
workmanship.
At a minimum, the project-specific QCP shall address:
1. Procedures for scheduling and coordinating the rigging, shut-down, and
installation phases with the COR.
2. Discrepancy identification and immediate corrective actions.
3. Refrigerant recovery logging and EPA-mandated tracking.
4. Verification checklist for pressure testing, dehydration, and charging.
5. Methodology for collecting and addressing government feedback.
Following contract award, three (3) copies of the comprehensive written QCP shall
be submitted to the Contracting Officer (KO) and Contracting Officer Representative
(COR) within five (5) working days for approval.
1.6.2 Quality Assurance
The government shall evaluate the contractor’s performance under this contract in
accordance with the Quality Assurance Surveillance Plan (QASP). This plan is a
government-only document focused on the methods the government will use to
assure that the contractor has performed in accordance with the metrics in
Technical Exhibit 1.
-- 3 of 26 --
1.6.3 Federal Government Holidays
The contractor is not required to perform routine work on Federal holidays. If
emergency or critical work is required on a holiday, it must be coordinated with the
COR at least 48 hours in advance. The recognized Federal holidays are:
• New Year's Day (January 1st)
• Martin Luther King Jr. Day (3rd Monday of January)
• Pr…
Source: SAM.gov, as posted. Verify the current solicitation before responding.