The Department of Defense is soliciting bids for two construction projects at the 179th Cyberspace Wing in Mansfield, Ohio, specifically for the B422 Breakroom and B300 BDOC, under NAICS code 236220. This opportunity is a total small business set-aside, suitable for small contractors with average annual revenues not exceeding $45 million. Bids will be evaluated without discussions, and interested bidders must register in the System for Award Management (SAM) to participate. The bid opening is scheduled for December 10, 2026, at 1:00 PM EST, and contractors are encouraged to attend a site visit as outlined in the solicitation.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
STATEMENT OF WORK
Project PBXP272019
B300 BDOC Renovation
MANSFIELD LAHM ANG BASE
MANSFIELD, OHIO
Table of Contents 1
General Requirements 2-3
Project Description 3-5
-- 1 of 5 --
2
1. General Requirements
1.1. The contractor shall provide all labor, supervision, materials, equipment, tools, transportation,
and incidentals necessary to renovate the B300 BDOC and Battlestaff spaces, including selective
demolition, wall repair, interior finish replacement, limited suspended ceiling modifications, and
associated electrical and communications pathway work required to support the revised room
layouts and new Government-furnished BDOC desks.
1.2. The location of the proposed work is within the main cantonment area of the Mansfield Lahm
ANG Base, Mansfield, Ohio.
1.3. The contractor shall not exceed the scope of work without prior approval from the Contracting
Officer.
1.4. The contractor shall protect all government property from damage. Any damages incurred in
pursuance of this project shall be replaced and/or restored to original condition.
1.5. The contractor shall maintain a clean and safe job site at all times to prevent damage to other
existing utilities, and surrounding facilities that may be affected; this is also intended to protect
building occupants from potential health hazard associated with the proposed work. This shall
include dust, debris, and waste created in performance of this project; along with tools,
equipment, and vehicles located at the job site. The contractor shall comply with the provisions
of the Occupational Safety and Health Act of 1972 and all provisions thereto.
1.6. The Contractor is responsible for properly laying out the work, and for lines and measurements
for the work executed under the Contract Documents.
1.6.1. The Contractor, not the Government, is responsible to field verify all utilities within the
project limits and/or as shown on the Drawings, before laying out the work. The Contractor
is to report errors or inaccuracies in writing to the Contracting Officer's Representative
before commencing work.
1.6.2. The Contracting Officer or his Representative will in no case assume the responsibility for
any layout of the work or damages to existing utilities while performance of work is
underway.
1.7. The Contractor shall field verify all dimensions. The dimensions provided by the Government
are only approximations and they are not responsible for their precision or accuracy. This
includes but is not limited to blueprints, drawings, schedules, and statements of work.
1.8. The contractor shall provide a one-year warranty for the work contained herein. They shall pass
along extended guarantees for equipment and products.
1.9. All trash, waste, and construction debris generated from this project shall become property of the
contractor and shall be removed from the base. The disposal of these materials shall follow the
appropriate Federal and State laws. This includes the disposal or recycling of hazardous
-- 2 of 5 --
3
materials. The contractor shall report the disposition of all waste to the COR on a quarterly
basis. Report shall detail weights of waste landfilled, diverted, and recycled.
1.10. Bids for this project shall be valid for 90 days.
1.11. Point of Contact for this project is Captain Clayton McCarthy at (419)-520-6158 or Mr.
Joe Logan at (419)520-6051.
2. Project Description
2.1. The contractor shall provide all labor, materials, equipment, supervision, transportation, and
incidentals necessary to renovate the B300 BDOC and Battlestaff spaces, including selective
demolition, wall repair, interior finish replacement, ceiling modifications, and associated
electrical and communications pathway work required to support the revised room layouts and
new Government-furnished equipment.
2.2. BDOC
2.2.1. The contractor shall perform selective demolition in the BDOC to remove the existing
controller desk, obsolete floor-fed utility components associated with the existing desk
arrangement, including the existing junction box, exposed power whips, and associated
miscellaneous components no longer required.
2.2.2. The existing communications floor penetration in the BDOC shall remain in place. The
contractor shall coordinate with the Government regarding capping and protection of the
penetration within the finished work.
2.2.3. The contractor shall prepare and repaint all BDOC wall surfaces.
2.2.4. The contractor shall prepare and repaint three (3) doors and associated frames as indicated
on the drawings.
2.2.5. The contractor shall remove existing floor finishes as required and furnish and install new
resilient tile flooring and new cove base throughout the BDOC.
2.2.6. The contractor shall prepare the existing floor substrate as required for the new flooring
system, including removal of failed or unsuitable existing coatings where required, minor
patching, leveling, adhesive removal, and localized repairs necessary for a complete
installation.
2.2.7. The contractor shall provide electrical modifications in the BDOC to support the new
Government-furnished controller desks, including relocation of existing floor-fed circuits to
wall-mounted devices within the finished wall assembly, as indicated on the drawings.
-- 3 of 5 --
4
2.2.8. The contractor shall provide communications pathway rough-in in the BDOC for the new
controller desk arrangement as indicated on the drawings. Communications cabling and
termination shall be coordinated with the Government unless otherwise directed.
2.2.9. The contractor shall remove and reinstall existing wall-mounted monitors and associated
mounting hardware in the BDOC at revised mounting elevations as indicated on the
drawings.
2.3. Battlestaff
2.3.1. The contractor shall perform selective demolition in the Battlestaff room as required to
remove obsolete or damaged finishes and accessories affected by the work, including
remaining wainscot materials as indicated on the drawings.
2.3.2. The contractor shall remove an…