What this opportunity is
The Department of Energy is seeking a supplier to design, fabricate, deliver, install, and commission a custom industrial furnace for research and development at Argonne National Laboratory in Illinois. This opportunity is open to all businesses, as there is no set-aside. Offerors must submit comprehensive proposals, including technical, business management, and pricing components, with a focus on technical acceptability for evaluation. Interested parties should note that this is a solicitation notice, indicating the need to prepare a bid rather than simply track the opportunity.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Argonne National Laboratory
Statement of Work
Custom R&D Box Furnace
October 12, 2026
1.0 Background
Argonne National Laboratory (ANL) requires a custom industrial furnace to support research and development (R&D) testing of fuel-flexible burner technologies. The furnace is intended to enable controlled thermal testing of direct- and indirect-fired burner configurations using natural gas and hydrogen fuel blends (0–100% H₂, balance natural gas).
This procurement is supported by an attached technical specifications document (the “Technical Specifications”), which includes the detailed technical requirements, interface expectations, and code/safety compliance references.
2.0 Scope
The Supplier shall design, fabricate, deliver, support installation, and commission a custom industrial furnace that meets the performance, functional, and compliance requirements stated in the Technical Specifications.
The scope of the supply is defined by the Technical Specifications and include the furnace, adaptable burner bung, furnace access door, refractory/insulation, cooling tubes, optical ports and windows, instrumentation ports, exhaust flue, and associated interfaces with the existing laboratory facility.
3.0 Objectives
The objectives of this procurement are to:
Provide a furnace system suitable for R&D burner testing within ANL’s facility environment, including support for direct-fired and indirect-fired configurations.
Deliver a furnace that achieves the thermal performance and operational capabilities stated in the Technical Specifications.
Ensure the furnace is designed, fabricated, installed, and commissioned in accordance with applicable codes, standards, and safety requirements identified in the Technical Specifications.
Establish a complete and usable set of deliverables (drawings, manuals, certificates, and test/commissioning records) to support safe operation and future maintenance.
4.0 Tasks
4.1 Furnace Design
The Supplier shall develop the design package for the custom furnace system, including engineering details sufficient for fabrication, procurement, and installation. The design shall incorporate, at a minimum, all required performance features and interface provisions described in the Technical Specifications.
Design activities shall include:
Performing engineering analysis and developing design solutions to meet the Technical Specifications and applicable codes.
Coordinating with ANL technical personnel through biweekly design meetings. Meetings shall be held remotely. The purpose of these meetings is to review design progress, address technical/interface questions, and ensure alignment. At each biweekly meeting, the Supplier shall provide a brief status update and raise items requiring ANL feedback or decisions.
Preparation of the design deliverables required by Section 5.2.
Submission of design package including engineering drawings for ANL review and approval prior to commencing fabrication.
Revision of requested modifications by ANL technical team
Obtaining written approval from ANL before commencing with fabrication of the furnace
4.2 Fabrication
The Supplier shall fabricate, assemble, and pre-test (as applicable) the furnace system at the Supplier’s facility to meet the Technical Specifications. The Supplier shall ensure workmanship, materials selection, and fabrication processes comply with the applicable codes/standards and the requirements of the Technical Specifications.
Fabrication activities shall include:
Procurement of all Supplier-furnished components.
Fabrication/Assembly of the custom furnace and subsystem hardware
Verification/quality control activities to support acceptance by ANL during and after installation.
Continued coordination with ANL through bi-weekly meetings to provide updates on fabrication progress, address questions, and ensure alignment.
4.3 Shipment
The Supplier shall prepare the furnace system for shipment, including handling, packaging, insuring, and securing for transport consistent with equipment sensitivity requirements. The Supplier shall deliver the shipped furnace components to the specified location for onsite installation as described in Section 8.0.
Shipment activities shall include:
Final inspection/packaging prior to shipment.
Provision of shipment/handling instructions and shipment documentation.
Coordination with ANL for receiving and logistics as required to complete installation.
4.4 Installation
The Supplier shall site the furnace system at ANL or provide installation instructions. If required, the Supplier will complete assembly of furnace system components onsite. ANL is responsible for making final utility (air, fuel, exhaust, coolant, etc.) connections to the furnace and mounting the burner.
A complete installation is constituted by:
The furnace is securely positioned at the agreed upon location and orientation at ANL.
Door retraction mechanism has been tested and confirmed operable and robust.
The exhaust system is connected to the furnace in compliance with the Technical Specifications and applicable codes.
Retractable cooling tubes are installed. Tube retraction mechanism has been tested and confirmed operable and robust.
Optical access windows are installed, and purge gas cooling system is tested and confirmed operable and robust.
4.5 Final Furnace Utilities Connection
ANL will make the final connection of utilities to the furnace, after it has been sited and installed. Utilities include combustion air, fuel (natural gas), coolant, exhaust stack (chimney). After final connections are made, ANL will schedule Furnace Commissioning (Task 4.6) with the Supplier.
4.6 Furnace Commissioning
The Supplier shall visit the ANL site to witness the first firing of the furnace with a natural gas direct-fired burner to perform functional checks of the furnace performance and identify/revise potential issues.
Commissioning activities shal…
Source: SAM.gov, as posted. Verify the current solicitation before responding.