What this opportunity is
The Department of Agriculture is seeking a contractor for roof and maintenance work at the Mesa Falls Visitor’s Center in Idaho Falls, Idaho, under a small business set-aside. The project includes reroofing, exterior painting, and minor repairs, with optional items for additional work on overhang framing and snow guards. This combined synopsis/solicitation notice indicates that interested small businesses should track the opportunity closely, as it may require a bid submission based on the detailed specifications provided.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
GENERAL SPECIFICATIONS
GAOA
SCOPE OF CONTRACT
SCOPE OF CONTRACT
This project consists of roof and other maintenance work on the Mesa Falls Visitor’s Center on the Caribou-Targhee National Forest to provide deferred maintenance work. The facility is operated by the Caribou-Targhee NF and Harriman State Park on the Ashton / Island Park Ranger District in Idaho Falls, Idaho. Reroofing, painting / staining the exterior, and other minor repairs will be part of the Base Bid, and snow guards and the repair of all round framing at all overhangs will be Optional Bid Items. The existing corrugated metal panel roofing and all metal trim and flashing will be removed and replaced. All exterior log walls, wood shingle walls, and all trim, doors, and windows will be prepped and stained / painted. Exterior woodpecker damage will be repaired as noted. Damaged overhang framing at one location will be repaired as noted. Work includes the removal and proper disposal of all demolished materials. Contractor shall provide all required materials.
Detailed descriptions of bid items are included in Section 000501, Repair Office Buildings.
Demolition and Construction sequencing shall be in accordance with the drawings and specifications and as follows:
Demolition – Remove existing roof materials according to drawings and specifications. Roof shall be stripped down to the existing roof sheathing. Remove all of the following.
Existing corrugated metal roof and underlying felts to expose sheathing.
All existing flashings. Existing flashings are not to be incorporated into new roof unless specifically called for.
Other existing roofing material as deemed necessary by the COR and contractor.
Prep log walls, wood shingle walls, and all trim.
Option: demo and remove rotten round framing at overhang.
Construction
Replace sheathing as necessary
Install ice and water shield over entire roof deck.
Install flashings, edge flashing, and drip edge.
Install metal roofing, ridge vents and ridge cap.
Stain log walls, wood shingle walls, and all trim.
Option: Install new round framing at overhang where removed.
PROJECT LOCATION
The Mesa Falls Visitor’s Center project site is located in Idaho Falls, Idaho at Upper Mesa Falls on Forest Service property.
SITE INFORMATION AND LIMITATIONS
The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
The contractor shall have partial use of the premises for construction operations, including partial use of the project site during the construction period. The Contractor’s use of the premises is limited by the Government’s right to perform work or to retain other contractor’s on portions of the Project. Dust protection and protection of employees is required.
Except as noted herein, all construction sites/ facilities included in the work will be occupied during construction. The work areas will be closed to the public during construction. The Contractor will be responsible for fencing, signing and limiting access. Access shall be maintained to the facilities other entrances throughout the construction period except as approved by the Contracting Officer.
The Contractor shall not disrupt existing utility service (water, power, telecom, sewer, etc.) to and within the compound without coordination and approval in writing from the Contracting Officer’s Representative. Provide 48 hours’ notice prior to disrupting utilities to the other occupied areas of the site.
Water is available at the site for construction purposes. The contractor is responsible for any temporary connection hardware.
Electricity is available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power (if any) for the site and the cost for the service.
Telephone service is not available and shall be the contractor’s responsibility.
Toilet Services are currently available. If the facilities become unavailable contractor is responsible for providing an alternative service.
Work hours allowed shall be Monday-Friday 7AM-7PM. The contractor may work weekends if needed, 8AM-7PM.
TRAFFIC CONTROL AND CONSTRUCTION SIGNING
No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the CO and Local Transportation Authority. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
Signing and barricades shall be adequate enough to protect Forest Service employees and public. The contractor shall take special care to adequately sign and protect areas of work and construction from persons using these areas.
WORK CAMPS, STAGING AND STORAGE AREAS
Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site. Overnight camping on site will not be allowed.
Confine storage of materials and equipment as approved by the Contracting Officer. The Contractor is responsible for the security of all personal equipment and materials.
No fuel storage is permitted on the site. Fuel trucks must be equipped with spill containment kits and portable berms that meet State and Federal regulations
INSPECTION OF WORKSITE
The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work …
Source: SAM.gov, as posted. Verify the current solicitation before responding.