Description
PERFORMANCE WORK STATEMENT
VISN 6 Water Management Contract
VISN 6 will solicit an annual service contract with four one-year option periods to provide services to test for legionella in facility/building potable water systems as identified in the attached VISN 6 Directive 1061 Water Sampling Requirements. The Offeror shall possess an understanding of the Government’s requirements and an understanding of the nature of the work to be performed under the prospective contract guidelines. The Offeror shall provide a technical team of qualified staff, partners, consultants, and sub-offeror to perform the work.
PERIOD OF PERFORMANCE
The base year/period shall be awarded July 1, 2026. Total period of performance shall be the base year/period plus four option years.
SCOPE OF WORK
Provide all the necessary services to provide guidance and monitoring for the seven VISN 6 facilities Water Management Programs (WMP). Contractor shall provide a minimum of 1 face-to-face meeting per year for each facility in February or March to review contract execution prior to the exercise of each option year. In Option Year 2, this meeting will also serve to review each facility’s WMP to ensure each facility’s WMP meets the current requirements of VA Directive 1061 Prevention of Healthcare-Associated Legionella Disease and Scald Injury from Potable Water Distribution Systems. This review shall be documented in a report to the COR with a copy to the technical manager at each facility by June 30, 2027.
Provide Legionella testing and the other data as identified in the attached VISN 6 Directive 1061 Water Sampling Requirements and the sample data spreadsheets, including Temperature, Residual/Total Cl and pH. Testing shall be accomplished quarterly in: Testing may be accomplished in other months, with the medical center POC approval. Facilities shall receive one-week notice prior to taking any samples, POCs identified are in the table below. Facilities shall receive all water testing results directly from the laboratory performing analysis and within 24 hours of release of laboratory reports. Each facility shall receive a full summary report within 15 days of the sample date.
Sampling shall be in accordance with CDC Legionella Sampling procedures and shall be a first draw sample. Samples are to be taken from both the hot and cold-water systems from the distal point of delivery. If the location to be sampled has a filter, the filter shall be removed and a first draw sample taken. The facility may ask for a discretionary sample to be taken after flushing the location, but the first draw must be taken and recorded. In order to obtain the hot water temperature, or if the fixture has mixing valves, water shall be flushed after the legionella sample is taken in order to record the water temperature.
If a building has ice machines, they will be tested quarterly and counted towards the building’s 20 samples. If the ice machine has a water dispenser, then the sample may be drawn from the dispenser, if not, collect ice from the bin or ice dispenser. Enough ice must be collected, such that when it melts, 250 ml of water is sent to the testing laboratory.
Data will also be input into 2 data upload spreadsheets provided at contract award (samples of the spreadsheets are attached). There will be one spreadsheet for building samples and one for tower samples provided to the POCs and COR named below. The data upload spreadsheet may change in minor aspects periodically, and the COR will provide updated spreadsheets to the contractor when this occurs. Contractor shall populate all columns, except Column G, Occupancy, which will be completed by the technical manager upon receipt of the completed spreadsheet. Contractor shall not change the spreadsheet format or columns. In columns that are not applicable, such as “Was PCR screening option chosen,” leave blank. The completed spreadsheets will be uploaded by the POCs to the national Water Safety Management Tool and cannot be altered.
Low Level and High-Level Remediation: Remediations shall be performed at the request of the COR. Low level remediation shall raise the residual chlorine level to 5 ppm, while high level remediation shall raise the residual chlorine level up to 200 ppm. For High level remediation, contractor shall supply at least 2 people to aid the facility in flushing to return the residual chlorine level to safe drinking water standards < 4 ppm.
The Contractor shall provide all labor, material, supplies, management and supervision
necessary to add chlorine in the injection point downstream of the backflow preventer,
disinfection of the potable water system. Water samples will be taken immediately following the hyper-chlorination for the required domestic water testing:
a. The contractor will open faucets at the furthest location from the point of injection
and verify that the drains can handle the flow.
b. The contractor will raise the levels to the required ppm and check by using
test strips at each water outlet and log each one. Signage will be provided by the
contractor to affix to the outlets.
c. Once the chlorine is brought into range at the last outlet, the levels will be
maintained for a minimum of 4 hours and up to 8 hours at the discretion of the POC with each fixture tested for chlorine residual to verify that the level is maintained at the required ppm. The levels will be checked at the outlets prior to the flushing by the contractor.
d. The contractor will then open all water outlets to flush the chlorine. The level
will be reduced to below 4 ppm at each outlet and recorded.
e. Once the levels are below 4 ppm, the contractor will remove the signs.
f. The contractor will provide a final report once the project is complete, including residual before during and after the remediation.
g. Test set-up shall be as follows:
VA Medical Center
Contact Information (site POC)
Address
Ci…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 541380)
mRNA-sequencing and Methyl-Bisulfite sequencing from submitted leaf tissue samples
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 4, 2026
Lagoon Sludge Survey, Sampling, and Analysis
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 29, 2026
J035--AIR TESTING AND CERTIFICATION
VETERANS AFFAIRS, DEPARTMENT OF · Sources Sought · due July 28, 2026
DNA Analyses
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 29, 2026
Radiological Services
NATIONAL TRANSPORTATION SAFETY BOARD · Combined Synopsis/Solicitation · due August 3, 2026
CO NP ROMO 10(98) TRAIL RIDGE RD GEOTECHNICAL INVESTIGATION
TRANSPORTATION, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 31, 2026