The Department of Veterans Affairs is soliciting bids for the Correct Stormwater Drainage project at the Salem VA Medical Center, under NAICS code 237110. This opportunity is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB), requiring them to perform at least 25% of the construction work. Interested contractors should note that this is a sealed bidding process, and they must be registered in the System for Award Management (SAM) to be eligible for award.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Project No. 658-23-108 100% Final Design
Correct Storm Water Drainage February 10, 2026
Salem VAMC
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 01-24
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements 05-24
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 13.31 Asbestos Transite Abatement 01-21
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
31 23 19 Dewatering 10-12
31 23 23.33 Flowable Fill 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 17 23 Pavement Markings 08-16
32 90 00 Planting 07-16
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 03-17
33 40 00 Storm Sewer 12-17
-- 1 of 277 --
Project No. 658-23-108 100% Final Design
Correct Storm Water Drainage February 10, 2026
Salem VAMC
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations,
including demolition and removal of existing structures, and furnish
labor and materials and perform work for the Salem VA Medical Center
Campus stormwater improvements as required by drawings and
specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Contracting Officer Representative (COR).
C. Offices of Mabbett & Associates, Inc., located at 105 Central Street,
Suite 4100, Stoneham, MA 02180, as Engineers, will render certain
technical services during construction. Such services shall be
considered as advisory to the Government and shall not be construed as
expressing or implying a contractual act of the Government without
affirmations by Contracting Officer or his duly authorized
representative.
D. Before placement and installation of work subject to tests by testing
laboratory retained by Department of Veterans Affairs, the Contractor
shall notify the COR in sufficient time to enable testing laboratory
personnel to be present at the site in time for proper taking and
testing of specimens and field inspection. Such prior notice shall be
not less than three workdays unless otherwise designated by the COR.
E. All general contractor and subcontractors employees shall comply with
VA security management program and obtain permission of the VA police,
be identified by project and employer, and restricted from unauthorized
access.
-- 2 of 277 --
Project No. 658-23-108 100% Final Design
Correct Storm Water Drainage February 10, 2026
Salem VAMC
01 00 00 -2
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction,
utility trenching and repair, cleaning of existing stormwater
infrastructure, roadway and sidewalk patching, re-paving and repairs,
grading, drainage and necessary removal of existing infrastructure.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where
the solicitation is posted. Additional copies will be at Contractor's
expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security
procedures that will remain effective for the entire duration of the
project.
2. The General Contractor is responsible for assuring that all sub-
contractors working on the project and their employees also comply
with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site
without appropriate badge. They may also be subject to inspection
of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s
notice to the COR so that security and arrangements can be provided
for the employees. This notice is separate from any notices
required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission
of the COR. Patients and staff are not to be photographed at any
time.
4. VA reserves the right to close down or shut down the project site
and order General Contractor’s employees off the premises in the
event of a national emergency. The General Contractor may return to
the site only with the written approval of the COR.
-- 3 of 277 --
Project No. 658-23-108 100% Final Design
Correct Storm Water Drainage February 10, 2026
Salem VAMC
01 00 00 -3
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock
combinations to the COR for the purpose of security inspections of
every area of project including toolboxes and parked machines and
take any emergency action.
2. The General Contractor shall turn over all permanent locks to the VA
locksmith for permanent installation.
D. Document Control:
1. Before starting any work, the General Contractor/Subcontractors
shall submit an electronic security memorandum describing the
approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all
drawings, project manual and other project information. This
information shall be shared only with those with a specific need to
accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may