1 OVERVIEW AND OBJECTIVE:
1.1 Overview:
1.1.1 This requirement is for nonpersonal services for the 5th Civil Engineer Squadron (CES),
5th Bomb Wing, Minot Air Force Base (AFB), including surrounding United States Air Force
locations within North-Central North Dakota as listed in this performance work statement.
1.1.2 Minot Air Force Base (AFB) is home to two major Air Force units: the 5th Bomb Wing
and the 91st Missile Wing. Located approximately 13 miles north of Minot, North Dakota, and
120 miles north of the state capital, Bismarck, Minot AFB experiences a continental climate with
warm summers and cold winters, as well as occasional extreme winds. The base operates in the
Central Time Zone. For more information, visit the following websites:
https://www.minot.af.mil/, https://minotnd.gov/, and https://visitminot.org/.
1.1.3 5 CES needs a Contractor to provide fire systems trainer maintenance, allowing the
Minot AFB Fire Department to train personnel on simulated fires and emergencies in a safe and
realistic manner.
1.2 Notes and Definitions:
1.2.1 While the term “Government” applies to the Government as a whole, only the CO’s, Fire
Department (FD) POC, Contract Administrator (CA), and Contracting Officer (CO) may supply
any guidance to the Contractor. The FD POC and CA help the CO in the administration of the
contract and may provide technical and administrative guidance. Only a warranted CO may bind
the Government to any changes in the terms or conditions to the contract.
1.2.2 The terms “Minot AFB”, “installation”, and “base” refer to all property and land
controlled by the 5th Bomb Wing and the 91st Missile Wing.
1.2.3 Personnel interactions:
1.2.3.1 If a government employee, such as a police or security officer, safety representative, or
Facility Manager, asks the Contractor to temporarily stop working, the Contractor must comply.
This includes stopping work during an emergency or when instructed to do so by emergency
-- 1 of 18 --
2
personnel. The Contractor must then notify the CO, CA, and COR within 24 hours about the
interruption and provide an estimate of the delay's impact.
1.2.3.2 If someone from the base, including customers or other personnel, asks the Contractor to
stop or change the work, the Contractor must NOT make any changes without the CO's approval.
If the Contractor is asked to stop or change the work, they must notify the CO, CA, and COR
immediately. The Contractor should direct any questions from base personnel to the CO to
ensure that all concerns are addressed properly.
1.2.4 Web links provided within this performance work statement are for informational
purposes and should not be considered contractual guidance.
1.3 Objective:
1.3.1 The Contractor is responsible for providing all personnel, equipment, tools, materials,
transportation, and supervision], to support this service, unless otherwise specified in this
performance work statement. The Government will only supply those items named in the
“Government Provided Facilities, Equipment, and Materials” section.
1.4 Description of Service:
1.4.1 5 CES needs Contractor provided fire systems trainer maintenance, allowing the Minot
AFB Fire Department to train personnel on simulated fires and emergencies in a safe and
realistic manner.
1.4.2 Historically the 5 CES has received these services through Service Contracts.
1.5 Codes and Standards:
1.5.1 Contractor work must follow the standards in this requirement and all proper local, state,
and federal or national codes. All work must conform to local installation facility standards when
shown. All products and equipment must be UL Solutions standards or equal. All codes and
standards must be the latest edition of applicable local, state, and federal or national codes at the
time of award.
1.6 Mobilization and Demobilization:
1.6.1 Mobilization / Phase-In Period:
1.6.2 The Government will provide a phase-in period of up to thirty (30) calendar days
commencing on the effective date of contract award. During this period, the Contractor shall
accomplish all initial administrative and onboarding tasks, including:
• Obtaining installation passes and Real ID-compliant base access credentials.
• Submitting the initial Contractor Quality Control Plan (QCP) and Safety Data Sheets
(SDS).
-- 2 of 18 --
3
• Designating primary and alternate Contract Managers.
• Conducting an initial joint inventory and facility walkthrough with the Fire Department
POC and Contracting Officer.
1.6.3 Full Operational Performance: The Contractor shall achieve full operational readiness
and assume full responsibility for all maintenance, emergency repair response times, and
reporting requirements in Section 2 no later than day thirty-one (31) post-award. All work
performed during or after the phase-in period shall comply fully with applicable technical orders,
NFPA standards, and safety directives.
1.6.4 Demobilization / Phase-Out and Transition: In the event the requirement transitions to
a successor contractor or reverts to in-house Government operation, the incumbent Contractor
shall cooperate fully to affect an orderly and professional transition. In accordance with FAR
52.237-3 (Continuity of Services), the Contractor shall ensure that normal trainer operations and
scheduled maintenance are not interrupted during the transition period.
1.6.5 Return of Government Property: Within ten (10) calendar days of contract expiration
or notification of non-selection for follow-on award, the Contractor shall return all government-
furnished property, tools, access badges, and materials to the Government in the condition
received, normal wear and tear excepted.
1.7 Place of Performance:
1.7.1 The primary place of performance is on Minot Air Force Base; Fire Department Training
Area located at Bldg. 2226 Bomber Blvd. The address for the central office of the 5 CES is
Building 445 Pea…