Description
PERFORMANCE WORK STATEMENT
FOR THE
PREVENTATIVE MAINTENANCE / REPAIR OF
OIL WATER SEPARATOR SYSTEMS
AT
JOINT BASE MCGUIRE-DIX-LAKEHURST
Joint Base McGuire-Dix-Lakehurst
5 November 2026
-- 1 of 14 --
PERFORMANCE WORK STATEMENT FOR
PREVENTATIVE MAINTENANCE / REPAIR OF
OIL WATER SEPARATOR SYSTEMS AT
JOINT BASE MCGUIRE-DIX-LAKEHURST
1. DESCRIPTION OF SERVICES. The contractor shall provide all management, tools, supplies,
equipment, and labor required to clean, inspect, and repair Oil Water Separator (OWS) systems at Joint
Base McGuire-Dix-Lakehurst.
1.0.1 To perform this mission, the Prime Contractor must directly hold, maintain, and provide proof
of the following specific equipment ownership/lease agreements and active personnel
certifications in the Prime Contractor's name at the time of proposal submission and
throughout the life of the contract:
Personal Certifications
• NJDEP A-901 Hauler License (N.J.S.A. 13:1E-126)
• 40-Hour HAZWOPER (OSHA 1910.120)
• Confined Space Entry (OSHA 1910.146)
• Certified OWS Alarm Technician License
Mission Equipment
• DOT-certified vacuum tankers
• Explosion-proof pumps
• Confined-space ventilation systems
• Certified waste storage tanks
1.1. BASIC SERVICES. The contractor shall perform preventative maintenance and repairs of
OWS systems, which consists of inspecting, testing alarms and sensors, emptying, cleaning,
recharging, and disposing of each system’s tanks, collection entry points, piping, vaults, and alarm
systems. The contractor shall dispose of the OWS systems’ contents at an appropriate disposal site
or treatment facility that complies with the Resource Conservation and Recovery Act (RCRA), as
well as all local, State, and Federal laws and regulations regarding waste disposal. For operational
guidance, the contractor shall strictly adhere to: Air Force Occupational Safety, Fire, and Health
Standards (DAFMAN 91-203, 25 March 2022); DODI 4715.6 Environmental Compliance (4 May
2015); Department of the Air Force Manual (DAFMAN) 32-1067 Water and Fuel Systems (4 August
2020); AFI 32-7001 Environmental Management (23 August 2019); Department of the Air Force
Instruction (DAFI) 23-201 Fuels Management (23 August 2023); 33 USC 1251 et seq., Clean Water
Act; and NJAC 7:14A New Jersey Pollution Discharge Elimination System. Specific workload
estimates are detailed in Appendix A.
1.2. CLEANING AND INSPECTION. Following schedule coordination and cleaning procedure
review with the Contracting Officer Representative (COR), the contractor shall isolate the oil-water
separator (OWS) vaults and pump out all contents including free-floating oil, contaminated
wastewater, sludge, and debris using specialized vacuum equipment, immediately halting
operations and notifying the COR if suspected hazardous materials are identified. Extracted waste
must be transported under a State-approved EPA waste manifest to a licensed Treatment, Storage,
and Disposal Facility (TSDF) under CLIN X004. The contractor shall pressure wash or steam clean
all collection entry points, interior chamber walls, tanks, piping, filters, screens, and media vaults
-- 2 of 14 --
(disassembling as needed), clearing and water-flow testing lines to verify the system is free of
obstructions. Upon COR approval of the cleaning, the contractor shall conduct a comprehensive
multi-point inspection adhering to manufacturer and industry standards including visual
assessments, nondestructive structural testing, and functional testing of floor grates, piping, valves,
catch basins, baffles, coalescing plates, protective coatings, and liquid-level alarms and complete
necessary repairs in accordance with paragraph 1.4. Prior to returning the unit to service, the
contractor shall recharge the system with fresh potable water using a reduced pressure zone (RPZ)
backflow preventer to the depth required to activate the hydraulic separation barrier, submitting a
comprehensive written inspection report to the COR within five (5) business days.
1.3. ALARM SYSTEMS. The contractor shall inspect and test all control monitoring systems to
include floats, wiring, lights, strobes, etc., to ensure all components of the alarm systems are in good
working condition.
1.4. REPAIRS. The contractor shall repair all mechanical, electrical, control, and safety
deficiencies because of the preventative maintenance and service calls. The contractor shall repair
the OWS equipment at the contractor’s expense if the material cost is less than $100.00 or less per
system. If the repair work is between $100.00 and $2,500.00 in total costs, the contractor shall
provide a written repair cost estimate to the COR within two (2) business days of finding the
deficiency requesting authorization to proceed. The written repair cost estimate shall include, at a
minimum, the following: the estimated cost of material, the labor hours needed to complete repairs,
and the projected time the equipment will be out of service. The contractor shall be financially
compensated for material and labor costs only if COR authorization is granted. At no time shall
work more than $100.00 be completed without COR approval. If the work exceeds $2,500.00 in
total costs, the contractor shall provide a written repair cost estimate directly to the Contracting
Officer (CO) only (not to the COR) within two (2) business days of finding the deficiency. The
written repair cost estimate shall include, at a minimum, the following: the estimated cost of the
material, the labor hours needed to complete the repairs, and the projected time the equipment will
be out of service. The contractor shall be financially compensated for the material and labor costs
only if CO authorization is granted. At no time shall work more than $2,500.00 be completed
without CO approval. There’s no maximum financial threshold for major repairs under this contract.
The contractor shall ensure all major repair work commences within three (3) days of COR or CO
approval. The contracto…