Description
Performance Work Statement (PWS)
WT 12895002
Bridge Redundant Power from Generator
Supply to Panel RP15 in Building 1470
Peterson Space Force Base (PSFB)
Colorado
19 October 2026
Mr. Timothy Ahlers 554-6721
Mr. Jeff Simon, 554-4992
-- 1 of 7 --
2
WT 12895002 Bridge Redundant Power from Generator Supply to
SMART-T in Building 1471
1. INTRODUCTION
1.1. The Contractor shall establish a redundant power infrastructure to support a
communications terminal. Primary power will be delivered from the currently
installed generator in Building 1471, with secondary redundant power sourced
from the Power Distribution Unit (PDU) located in Building 1470, Room 126.
To support this terminal, the contractor must run dedicated electrical feeds
approximately 100 feet from the PDU in Room 126 to Electrical Panel RP15
located in building 1470 hallway. The installation must deliver the following
dedicated circuits to the terminal's breakers: Two (2) x 20-Amp (A) circuits
and One (1) x 30-Amp (A) circuit.
1.2. The Contractor shall provide all labor, materials, equipment, and resources
necessary to complete the installation of power run from Building 1470 Room
126 to Electrical Panel RP15 and existing red PDU at Peterson Space Force
Base, Colorado, as defined in this Performance Work Statement (PWS). All
work must comply with applicable federal, state, and local regulations,
including Occupational Safety and Health Administration (OSHA), Unified
Facilities Criteria (UFC) 3-520-01-Interior Electrical Systems, National
Electrical Code (NEC), National Fire Protection Association (NFPA) 70 and
70E, Peterson SFB Design Guide and manufacturer standards.
2. GENERAL REQUIREMENTS
2.1. The Contractor is responsible to verify site conditions, measurements,
quantities, and materials needed to complete this project prior to submitting a
proposal.
2.2. Estimated Performance Time: 105 calendar days. This includes 60 days for
site survey, planning, coordination, and procurement, and 30 days for labor.
2.3. All work accomplished by the Contractor shall comply with the contract
criteria unless a waiver is obtained from the Air Force when conditions
warrant such consideration. All construction work shall be subject to
stoppages and delays due to critical PSFB mission requirements.
-- 2 of 7 --
3
WT 12895002 Bridge Redundant Power from Generator Supply to
SMART-T in Building 1471
2.4. The Contractor shall, within five days after the Notice to Proceed (NTP) (or
timeframe determined by the Contracting Officer), submit a practicable
electronic work schedule for approval. This schedule should detail the order
of work, anticipated start and completion dates for key tasks, and be
presented as a progress chart.
3. PROJECT SCOPE
3.1. The PDU’s Automatic transfer switch currently supports all the requirements
of the current connections. It will, however, need to be verified for capacity
to support the additional (2) 20A and (1) 30A requirements. Due to the
nature of the mission supported by the terminal, the outage time for the final
connection of the communication terminal to the new redundant circuit must
be as short as possible. If possible, the final cutover must be completed
within a single, scheduled outage window not to exceed four (4) hours.
3.2. The contractor shall label all new conduits, junction boxes, and breaker
panel circuits according to ANSI/TIA-606-C standards or, if no standard is
specified, with professional, machine-printed labels detailing the power
source and circuit ID.
3.3. Any potential outages to building power or other circuits must be scheduled
with at least 14 days of notice and adhere to a predetermined timeframe.
Additionally, any outages of the communication terminal power must be
scheduled with at least 7 business days of notice and adhere to a
predetermined timeframe.
3.4. A final test must be conducted to ensure proper operation of communication
terminal during simulated outage. This may require coordination with 21
CES personnel to schedule a time for the generator to turn on and run for the
required amount of time to test. The final acceptance test shall consist of a
simulated utility power outage. The system must demonstrate a successful,
automatic transfer to generator power. The total power interruption to the
communication terminal equipment shall not exceed the time specified by
the equipment manufacturer's power-holdup specifications to ensure
continuous operation.
-- 3 of 7 --
4
WT 12895002 Bridge Redundant Power from Generator Supply to
SMART-T in Building 1471
3.5. Upon completion of the work, the communications terminal will have a
power branch circuit installation connecting it to the Red PDU and
Automatic Transfer Switch in Room 126.
3.6. The Contractor shall conduct a comprehensive electrical commissioning test
on the newly installed branch circuits and feeders to verify proper
connectivity and seamless failover between the communication terminal and
the auxiliary generator.
3.7. To achieve final testing approval, the Contractor shall coordinate and
execute a utility power outage simulation. During this test, primary
commercial utility power to the facility shall be disconnected to initiate
automatic generator startup and load transfer. The test shall successfully
demonstrate that the generator assumes the electrical load and delivers
stable, continuous power to the communication terminal without interruption
or degradation of service.
4. UTILITY OUTAGES
4.1. Any required outages (i.e., electrical, HVAC, utilities, fire alarm, fire
suppression, etc.) shall be formally requested through Customer Service at
719-556-4330. Fire alarm outages should be requested 3 days ahead, while
all other outages shall be requested 14 days in advance.
5. HOT WORK PERMIT
Hot work shall be coordinated a minimum of 7 days in advance from the Fire
Department Prevention Office with contact at 719-556-6574. The contractor
shall complete a one-time hot work training class at …
Source: SAM.gov, as posted. Verify the current solicitation before responding.