What this opportunity is
The USDA is seeking design/build services for perimeter security enhancements at Parking Lot 9 of the Jamie L. Whitten Building in Washington, DC. This opportunity is open to all businesses, as there is no set-aside for small businesses. Interested contractors should note that the solicitation is a combined synopsis/solicitation, indicating a need to track the opportunity closely rather than submit a formal bid at this stage. The project involves working near sensitive infrastructure, which adds complexity to the execution.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
SCOPE OF WORK Design/Build Perimeter Security Enhancement Parking Lot 9, 12th Street
USDA Headquarters Jamie L. Whitten Building, Washington, DC 20250
Solicitation # 124PCA27Q0002
Page 1 of 9
SCOPE OF WORK
Design/Build Perimeter Security Enhancement
Parking Lot 9, 12th Street
USDA Headquarters Jamie L. Whitten Building
Washington, DC 20250
dated November 19, 2026
1. BACKGROUND
The United States Department of Agriculture (USDA) Headquarters (HQ) Complex in Washington
D.C. consists of two buildings: the Jamie L. Whitten and the Agriculture South Buildings, both of
which are listed on the National Register of Historic Places and as such are subject to the Section
106 Historic Preservation Review Process for any modifications. The headquarters buildings are
classified as Level IV facilities. In 2014, the USDA commissioned an A/E firm to develop the
“Concept Site Improvements and Perimeter Security Plan,” because the Department’s perimeter
requires hardening to prevent unauthorized motor vehicle entry. The Concept Plan was approved
by the General Services Administration (GSA), the District of Columbia State Historic Preservation
Officer, the District of Columbia Archeologist (DCA), the National Park Service (NPS), the
Commission of Fine Arts (CFA) and the National Capital Planning Commission (NCPC). The GSA,
CFA and NCPC approved the design development for the perimeter security enhancement at
Parking Lot 9 of the Whitten Building, which is the site of the Farmers Market. It is held every Friday
between May and October, drawing large crowds of employees and tourists. The Lot 9 construction
was underway; unfortunately, it was deemed to be in the best interest of the government to allow
the construction contract to expire. The Washington Metropolitan Area Transit Authority (WMATA)
orange, blue and silver line infrastructure is less than 7’-0” below the Lot 9 parking surface, making
excavation high risk.
USDA requires further development of the original Lot 9 construction document package dated
April 16, 2021. The design package is the construction bid set for the perimeter security
enhancements at Parking Lot 9. The oversight authorities have already approved the Lot 9 design,
necessitated because of its prominent location adjacent to the National Mall. Additional approvals
are not necessary unless the design substantially changes. Other required approvals will include
the Washington Metropolitan Area Transit Authority (WMATA) as portions of Lot 9 are located
directly over the Smithsonian Metro Station and the District Department of Transportation (DDOT)
which owns the sidewalk surrounding Lot 9 at the east and south boundaries.
The A/E who developed the Lot 9 design concept, obtained approval from the oversight authorities.
Subsequently, the A/E created drawing and specification documents for the Lot 9 perimeter
security enhancement project based upon the approved design. The drawing and specification
documents, dated April 16, 2021, detail the project requirements in general. Though the provided
-- 1 of 9 --
SCOPE OF WORK Design/Build Perimeter Security Enhancement Parking Lot 9, 12th Street
USDA Headquarters Jamie L. Whitten Building, Washington, DC 20250
Solicitation # 124PCA27Q0002
Page 2 of 9
specifications and drawings may appear to be fully engineered solutions they cannot be relied upon
to be such for any portion of the work. Shortly after the construction contractor began work in
February 2024, a sink hole developed in the southwest portion of the site requiring remediation.
The WMATA engineers have examined the sinkhole. The results of Langan’s site surveys and
remediation recommendations are in a report dated January 28, 2026. The D/B contactor must
ultimately determine the full extent of the sink holes and develop a remediation plan approved by
WMATA in accordance with Langan’s recommended solution Option #2. The Lot 9 north boundary
will require an engineered solution, either a stepped mud mat foundation or shimming of the
shallow footed bollards with appropriate steel shapes or concrete blocks to ensure the top of each
bollard is at least 36” above grade and certified by the bollard manufacturer Guardiar, or approved
equal, as meeting a crash rating of M50/P1. While it is desirable to utilize the bollards on site, the
purchase of taller bollards for the north border is a potential solution. The Design-Build (D/B)
contractor is responsible for fully developing the design drawings, details, and construction
specifications to meet performance specifications. WMATA will review the all Design packages &
submissions. The drawings/sketches and details shown on the original A/E packages dated April
16, 2021, are program requirements only and not considered as a final design package. The D/B
contractor is responsible to propose innovative means and methods to achieve the full scope of
the work.
No work has been performed on site since the summer of 2025. The original contractor completed
the mud matt foundation for the shallow footed barriers, the installation of the streetlamps along
12th Street, the hydraulic (moveable) bollards, power boxes at the center of the lot, and the building
identification signs at the four corners of the property. Of the work completed, some will require
demolition or modification. Additionally, four lengths of granite curb, the 63 shallow footed
bollards, accompanying bollard covers, and 12 of the 13 deep footed bollards were delivered to the
site. A construction fence encloses the site.
2. OBJECTIVE
Provide Level 4 perimeter security enhancement for the Jamie L. Whitten Building at Parking Lot 9,
updating the original construction documents (drawings and specifications) as necessary,
following determination of areas requiring demolition and sink hole remediation by continuing
construction where the original contractor stopped work. The Design-Builder shall incorporate all
referenced documents and requirements into the updated construction documents, as app…